Tuesday, April 25, 2017

Building Update - Week of April 17th

Drywall continues to go up throughout the building. Concrete patching throughout.
The lower level floor is being prepped , and when it is poured all of the new floors will be complete. 
Preparation on the roof and the west side of the building for the big crane on the west side of the building to lift HVAC  equipment and transformers onto the roof.Excavation for waterproofing on the south side of the building. 
Window installation continues 

Lower level floor is being prepped for pouring. When complete all floors will be installed.


Drywall installation

New staircase

Drywall



Drywall

Elevator shaft

HVAC ducts

Ready for drywall



Vapor barrier system installed and floor prep continues

Top of the elevator shaft

Staircase




New Window installation proceeds on south side, on the 4th and 3rd floors

Excavation on south side of building for waterproofing










Drywall

Wednesday, April 12, 2017

April 12 Bulding Project Update

April 12, 2017

The cleaning and the repairs to the south side of the building are complete. You can see a scaffolding in place here, and one of the many new windows that are being installed. 

And the new windows open!

The wall framing is complete on every floor.  Trade workers - plumbing, electrical, HVAC and fire suppression are installing their utilities throughout the building.





The floor in the gym is being prepped for new concrete.  All the other floors have all been poured.




Drywall was delivered to the third floor via remote control.  The crane was operated by the delivery driver who was inside the opening on the third floor


Exterior cleaning and repair moves to the north face of the building. Cleaning and repairs take place before the installation of the windows.

The former freight elevator shaft is being turned into a new staircase.

Also this week, waterproofing on the south wall of the building started and work continues roughing in electrical and firepump rooms.