Drywall continues to go up throughout the building. Concrete patching throughout.
The lower level floor is being prepped , and when it is poured all of the new floors will be complete.
Preparation on the roof and the west side of the building for the big crane on the west side of the building to lift HVAC equipment and transformers onto the roof.Excavation for waterproofing on the south side of the building.
|
Window installation continues |
|
Lower level floor is being prepped for pouring. When complete all floors will be installed. |
|
Drywall installation |
|
New staircase |
|
Drywall |
|
Drywall |
|
Elevator shaft |
|
HVAC ducts |
|
Ready for drywall |
|
Vapor barrier system installed and floor prep continues |
|
Top of the elevator shaft |
|
Staircase |
|
New Window installation proceeds on south side, on the 4th and 3rd floors |
|
Excavation on south side of building for waterproofing |
|
Drywall |
No comments:
Post a Comment